Identifikasi dan Penilaian Risiko Stakeholder pada Proyek Infrastruktur Pertambangan Nikel
Studi Kasus di Pertambangan Nikel PT. X
DOI:
https://doi.org/10.58169/jwikal.v5i1.1094Keywords:
Mining Infrastructure, Nickel Mining, Risk Identification, Risk Mitigation, StakeholdersAbstract
The growth of the nickel mining industry in Indonesia, particularly in Southeast Sulawesi Province, has made this sector one of the main contributors to the Regional Gross Domestic Product (RGDP). However, the development of supporting infrastructure—especially mining haulage roads—still faces various risks that could potentially cause project delays and disrupt operational efficiency. Therefore, a systematic risk identification process is necessary to ensure that project implementation proceeds in accordance with established time, cost, and quality targets. This study aims to identify and assess risks in mining infrastructure development projects using a stakeholder-based approach. This approach is employed to gain an understanding of the risks that arise from the perspectives of the parties involved in the project. The results of this study describe the dominant risks that could potentially occur in nickel mining projects, namely opposition from the local community surrounding the project, conflicts with community organizations, denial of access to project roads, and disruption of project security due to inadequate security measures by authorities. It is hoped that these dominant risks can serve as a basis for developing effective risk mitigation strategies to support the successful and sustainable development of mining infrastructure.
References
Aaltonen, K., Jaakko, K., & Tuomas, O. (2008). Stakeholder salience in global projects. International Journal of Project Management, 26(5), 509–516.
Abdulwahab Al Geelani, et. al. (2021). Investigation of Project Delivery Risks in Public-Private-Partnership (PPP) Infrastructure Projects in UAE - A Stakeholder’s Perspective. IEEE Xplore, 1-5.
Almaian dan Bu Qammaz. (2017). Project Risk Management: The Role of Stakeholder Analysis. Proceedings of the International Conference on Industrial Engineering and Operations Management, Bandung, Indonesia, March 6-8, 2018.
Amiruddin et al. (2022). Strategic Analysis of the Implementation of Stakeholder Involvement in Risk Management in Mining and Mineral Companies. Budapest International Research and Critics Institute-Journal (BIRCI-Journal), 5(2), 1234-1245.
Ana Rita, et. al. (2024). Stakeholder Management and Communication Management in Non-Govermental Organizations: A Systematic Literature Review. Procedia Computer Science, 239 (2024) 1942–1949.
Anas S., et. al. (2024). Management of Stakeholder Engaged in Port Energy Transitions. Energy Policy, 188(114074), 1-18.
Ariana, I. K. A., Dharmayasa, I. G. N. P., dan Riana, I. N. (2023). Identifikasi Faktor-Faktor Risiko Pada Proyek Infrastruktur Dasar dan Fasilitas Umum Penunjang Pariwisata di Pelabuhan Benoa, Bali. Jurnal Teknik Sipil Universitas Warmadewa, 12(1), 114-120.
Arikunto, S. 2000. Prosedur Penelitian Suatu Pendekatan Praktek. Jakarta: Rineka Cipta.
Asri Nurdiana, et. al. (2015). Sensitivity analysis of risk from stakeholders’ perception Case study: Semarang-Solo highway project section I (Tembalang-Gedawang). Procedia Engineering, 125, 12-17.
Badan Pusat Statistik Provinsi Sulawesi Tenggara (2019). Provinsi Sulawesi Tenggara Dalam Angka. Badan Pusat Statistik Provinsi Sulawesi Tenggara.
Chandra, H.P, Indarto, Wiguna, I. P. A., dan Kaming, P. (2011). Peran Kondisi Pemangku Kepentingan Dalam Keberhasilan Proyek. Jurnal Manajemen dan Kewirausahaan, 13(2), 135-150.
Dana Kusumo, et. al. (2019). Analyzing Differences in Risk Perceptions between Developers and Acquirers in OTS-based Custom Software Projects Using Stakeholder Analysis. IEEE Xplore, 69-78.
Dandage, R. V., & Mirji, H. (2022). Planning the Appropriate Risk Response Strategies by Exploring and Prioritizing the Risk Categories in International Projects. Polaris Global Journal of Scholarly Research and Trends, 1(4), 52–60.
Daniele Bertolozzi, et. al. (2021). Stakeholder Perspectives to Improve Risk Management in European Farming Systems. Juornal of Rural Studies, 84, 147-161.
Darmastuti, L., Rustiadi, E., Fauzi, A., & Purwanto, Y.J. (2023). Stakeholder Analysis of Sustainable Wastewater Management: A Case Study of Bogor, Indonesia. Sustainability, 15, 1-24.
Dewi, R., Soemardi, B. W., & Waty, M. (2025). Analisis Tantangan dan Pengelolaan Risiko Proyek Pembangunan Ibu Kota Nusantara dengan Pendekatan Kualitatif. Media Ilmiah Teknik Sipil. 13(1), 1-8.
Dong Zhao, et. al. (2016). Stakeholder Perceptions of Risk in Construction. Safety Science, 82, 111–119.
Dumas, M., La Rosa, M., Mendling, J., & Reijers, H. A. (2018). Fundamentals of Business Process Management (2nd ed.). Springer.
Dwi Rizky Cahyani, Rahman Rahman, Ega Apridian, Arian Syahri, & Dwi Rizka Zulkia. (2025). Analisis Persepektif Multi-Stakeholder terhadap Pengembangan Taman Kehati Hutan Pelawan dengan Konsep Healing Forest sebagai Inovasi Pariwisata Berkelanjutan. Konstruksi: Publikasi Ilmu Teknik, Perencanaan Tata Ruang Dan Teknik Sipil, 3(4), 73–87. https://doi.org/10.61132/konstruksi.v3i4.1111
Emily H., et. al. (2024). Qualitative Approach to Measuring Stakeholder Risk Perceptions of Mytocoxins in the Midwest Grain Supply Chain. Food and Humanity, 3, 1-10.
Enderzon, V. Y., & Soekiman, A. (2020). Manajemen Risiko Proyek Konstruksi Flyover di Indonesia dengan Metode House of Risk (HOR). Media Teknik Sipil, 18(1), 57-68.
Eyieyien, O.G., Idemudia, C., Paul, P. O., dan Ijomah, T. I. (2024). Effective stakeholder and risk management strategies for large-scale international project success. International Journal of Frontiers in Science and Technology Research, 07(01), 013–024.
Ezzy Cardila Vertiwi, et al. (2025). Tinjauan Pustaka Sistematis: Inovasi Hijau pada Nilai Perusahaan dengan Kinerja Keuangan sebagai Variabel Mediasi: Bukti dari Industri Pertambangan. Populer: Jurnal Penelitian Mahasiswa, 4(4). https://doi.org/10.58192/populer.v4i4.4067
Flanagan, R., & Norman, G. (1993). Risk management and construction (1st ed.). Blackwell Science.
Freeman, R. E. (2020). Strategic Management: A Stakeholder Approach (Revised Edition). Cambridge University Press.
Gabriela Fernandes, et. al. (2021). A Stakeholders' Perspective on Risk Management for Collaborative University-Industry R&D Programs. Procedia Computer Science, 181, 110-118.
Ghifari, R. B. M., Fitria, S., Rahmaniati, A. F., dan Yakin, M. A. (2015). Pemodelan Proses Bisnis Manajemen Proyek Berdasarkan Project Management Body of Knowledge (PMBOK). Journal of Computer Science and Applied Informatics, 4(1), 1-24.
Hande Aladag, et. al. (2020). The Effect of Stakeholder-Associated Risks in Mega-Engineering Projects: A Case Study of a PPP Airport Project. IEEE Transactions on Engineering Management, 67(1), 174-186.
Hatmoko, J.U.D., Putri, D.M., & Hermawan, F. (2020). Analisis Power-Interest Stakeholder terhadap Asuransi Bencana Infrastruktur Publik di Kota Semarang. Media Komunikasi Teknik Sipil, 26(2), 220-228.
Hillson, D. (2009). Managing risk in projects (2nd ed.). Gower Publishing.
International Federation of Consulting Engineers (FIDIC). (2017). Conditions of contract for construction for building and engineering works designed by the employer (2nd ed.). FIDIC.
Jason Xin, et. al. (2023). Modelling Stakeholder-Associated Productivity Performance Risks in Modular Integrated Construction Projects of Hong Kong: A Social Network Analysis. Journal of Cleaner Production, 423(138699), 1-16.
Juan, J., Shalaho Dina Devy, Revia Oktaviani, Tommy Trides, & Ardhan Ismail. (2025). Studi kasus sistem penyaliran tambang batuabara pt bukit baiduri energi kabupaten kutai kartanegara provinsi kalimantan timur: -. Globe: Publikasi Ilmu Teknik, Teknologi Kebumian, Ilmu Perkapalan, 3(3), 77–87. https://doi.org/10.61132/globe.v3i3.948
Kementerian Energi dan Sumber Daya Mineral. (2021). Keputusan Menteri Energi dan Sumber Daya Mineral Republik Indonesia Nomor 139.K/HK.02/MEM.B/2021 tentang Pemenuhan Kebutuhan Batubara Dalam Negeri. Kementerian Energi dan Sumber Daya Mineral Republik Indonesia.
Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). John Wiley & Sons.
Loosemore, M., Raftery, J., Reilly, C., & Higgon, D. (2012). Risk management in projects (2nd ed.). Routledge.
Muhammad Alwan Ramadhana, et al. (2024). Gugatan Uni Eropa Terhadap Pembatasan Ekspor Nikel Indonesia. Doktrin: Jurnal Dunia Ilmu Hukum dan Politik, 2(2). https://doi.org/10.59581/doktrin.v2i2.2608
Nugraha & Arief Pambudi (2025). Peran Gradasi dan Mineralogi dalam Menentukan Kekuatan dan Kompresibilitas Material Disposal Tambang Nikel: Kajian Literatur. Venus: Jurnal Publikasi Rumpun Ilmu Teknik, 3(6). https://doi.org/10.61132/venus.v3i6.1209
Olander, S. (2007). Stakeholder impact analysis in construction project management. Construction Management and Economics, 25(3), 277–287.
Pitangueira, et. al. (2017). Minimizing the stakeholder dissatisfaction risk in requirement selection for next release planning. Information and Software Technology, 87, 104–118.
Prihartono, B., Annasthacia, G. A. P., & Fahlevi, F. (2023). Perancangan strategi pengelolaan risiko pemangku kepentingan berbasis proses bisnis pada PT X. J@ti Undip: Jurnal Teknik Industri, 18(2), 120–129.
Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK® guide) (7th ed.). Project Management Institute.
Ward, S., & Chapman, C. (2003). Transforming project risk management into project uncertainty management. International Journal of Project Management, 21(2), 97–105.
Yang, J., Shen, G. Q., Ho, M., Drew, D. S., & Chan, A. P. C. (2011). Exploring critical success factors for stakeholder management in construction projects. Journal of Civil Engineering and Management, 17(3), 337–348.
Zou, P. X. W., Zhang, G., & Wang, J. (2007). Understanding the key risks in construction projects in China. International Journal of Project Management, 25(6), 601–614.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 JURNAL WILAYAH, KOTA DAN LINGKUNGAN BERKELANJUTAN

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.