Analisis Produktivitas Tenaga Kerja Terhadap Biaya Dan Waktu Pelaksanaan Pada Pekerjaan Pembangunan Proyek DPT Sungai Watudakon Mojokerto

Authors

  • Bagas Ramadhani Universitas 17 Agustus 1945 Surabaya
  • Wateno Oetomo Universitas 17 Agustus 1945 Surabaya

DOI:

https://doi.org/10.58169/jusit.v1i1.147

Keywords:

Productivity, Waste of Time, Work Effectively and Efficiently

Abstract

The purpose of this study is to determine labor productivity against costs and time of implementation of the Watudakon River DPT project development work. The results of this study are the large number of labor productivity in the construction work of the Watudakon River DPT project, Mojokerto. With the results of calculating the overall productivity level, namely with an average of 2,228 m³/day, assuming 25% of formwork material shunting work and 75% installation of formwork, the calculation data is in accordance with what is carried out in the field. Duration of implementation according to a survey conducted on DPT Sungai Watudakon construction work, Mojokerto with an average value of duration for installation of pile cap formwork 1.013 days/hour, and for installation of DPT wall formwork 1.00 days/hour, then for pile repair work DPT cap and wall 1.00 days/hour, and also for pile cap casting work 1.166 days/hour, for DPT wall casting work 1.312 days/hour. The conclusion in this study is that the productivity of the workforce working hours is in accordance with the realization in the field and that work results can be increased by adding working hours or overtime.

References

Asher Prasetyo, D., Pintardi Chandra, H., & Soehendro Ratnawidjaja, dan. (2017). ANALISIS PRODUKTIVITAS TENAGA KERJA DENGAN METODE WORK SAMPLING: STUDI KASUS PROYEK TUNJUNGAN PLAZA 6.

Cornelia, B. (2003). Analisa Produktivitas Tenaga Kerja Dalam Kaitannya Terhadap Waktu Dan Pelaksanaan Proyek Kontruksi. (Tugas Akhir). Program Studi Teknik Sipil Fakultas Teknik Universitas Udayana.

Dipohusodo. I. (1996). Manajemen Proyek & Konstruksi. Kanisius.

Erviant. (2005). Manajemen Proyek Kontruksi (Edisi Revisi). ANDI.

H Kerzner. (2009). Project Management : A System Approach to Planning, Scheduling, and Controling (Tenth). John Wiley & Sons.

Hardiyatmo, H. C. (2014). Analisis dan Perancangan Fondasi 1 . Gajah Mada University Press.

Husein Umar. (1998). Riset Sumberdaya Manusia Dalam Organisasi. PT. Gramedia Pustaka Utama.

Iman Soeharto. (1999). Manajemen Proyek (Dari Konseptual Sampai Operasional) (Jilid 1). Erlangga.

Indra Arisandi, I Gede Putu Warka, & Zaedar Gazalba. (2018). ANALISIS KEBUTUHAN TENAGA KERJA DAN PERALATAN PADA PROYEK PENINGKATAN JALAN Studi Pada Pelaksanaan Proyek Peningkatan Jalan Pancor-Rempung. http://journal.unmasmataram.ac.id/index.php/GARA

Kartika, N., Robial, S. M., & Agung, P. (2020). Analisis Produktivitas Tenaga Kerja Pada Pekerjaan Kolom Di Proyek Pembangunan Gedung Pemda. Jurnal Momen 03(02), 103–112.

M Husen Abrar. (2009). Manajemen Proyek. CV Andi offset.

Mawardi. (2021). ANALISIS PRODUKTIVITAS TUKANG DAN HARGA SATUAN PEKERJAAN PASANGAN DINDING BATA MERAH DAN BATA RINGAN (ANALYSIS OF LABOR PRODUKTIVITY AND UNIT PRICE WORK FOR PAIR OF BRICK AND LIGHT BRICK WALLS.

Messah, Y. A., Waktu, P., Biaya, D., Konstruksi, P., Dampak, S., Desain, P., Waktu, P., Perubahan Desain, D., Kasus, S., Oenaem, E. I., Selatan, K. B., & Messah, Y. A. (2013). Kabupaten Timor Tengah Utara). In Jurnal Teknik Sipil: Vol. II (Issue 2).

Muh. Luthfi Asyir Suhaeb. (2020). ANALISIS KOEFISIEN PRODUKTIVITAS TENAGA KERJA PADA PEKERJAAN PASANGAN BATA (ANALYSIS OF LABOR PRODUCTIVITY COEFFICIENCY ON BRICKWORK).

Pratama, & Rizky. (2021). Analisis Produktivitas Tenaga Kerja Di Lapangan Pada Pekerjaan Kolom.

Rizqa Karima, B., Khamim, M., Setiono, J., Manajemen Rekayasa Konstruksi, M., Teknik Sipil, J., Negeri Malang, P., Jurusan Teknik Sipil, D., kunci, K., & Bertulang, B. (2020). ANALISA PRODUKTIVITAS TENAGA KERJA BERDASARKAN PERMEN PUPR DAN PERHITUNGAN LAPANGAN PEKERJAAN BETON BERTULANG PROYEK APARTEMEN BESS MANSION. In JOS-MRK (Vol. 1, Issue 2). http://jos-mrk.polinema.ac.id/

Soeharto. (1995). Manajemen Proyek Dari Konseptual Sampai Operasional (Edisi Pertama). Erlangga.

Sutrisno, E. (2009). Manajemen Sumber Daya Manusia (Edisi Pertama). Kencana Prenada Media Group.

T Hani Handoko. (1999). Manajemen. BPFE Yogyakarta.

Tanjung, Amalia, Afrisa, & Yesi. (2016). Perencanaan Dinding Penahan Tanah Tipe Penyanggah Pada Tebing Sungai Lematang Kabupaten Lahat, Sumatera Selatan.

Toma Mandani. (2010). ANALISIS PRODUKTIVITAS TENAGA KERJA PADA PEKERJAAN PASANGAN BATA ANALYSIS OF LABOUR’S PRODUCTIVITY ON BRICKWORK (A Case Study of Development Project of Dr. Moewardi Hospital, Surakarta, Central Java).

Tomas Aprilian. (2010). ANALISIS PRODUKTIVITAS TENAGA KERJA PADA PEKERJAAN STRUKTUR RANGKA ATAP BAJA.

Downloads

Published

2023-06-23

How to Cite

Bagas Ramadhani, & Wateno Oetomo. (2023). Analisis Produktivitas Tenaga Kerja Terhadap Biaya Dan Waktu Pelaksanaan Pada Pekerjaan Pembangunan Proyek DPT Sungai Watudakon Mojokerto. Jurnal Sipil Terapan, 1(1), 82–93. https://doi.org/10.58169/jusit.v1i1.147